Keikyu Corporation — Continuous Grade Separation Project near Kamata Station

Details A temporary staging platform was built over the existing tracks. Factory-fabricated girders were placed on this platform and then slid into their final positions.
Load conditions: launching nose, rails, bogies and erection girder section = 45 t
Travel area of the 4.9 t crawler = 10.3 t